Let Contractors Sue for Delays

Official title

“Relates to damages to contracts occasioned by delay”

Sponsor Michael H. RanzenhoferSD-61+1 co-sponsorAffects Finance
Status
Vetoed
Impact
6/10
Moderate
Outcome
Vetoed

Bill progress

Vetoed

What's happening

This bill requires public contracts to include provisions allowing contractors to claim additional costs caused by delays attributable to acts or omissions by public entities.

Why it matters

  1. Shifts financial risk for delays. The bill ensures that public contractors can recover actual costs (not just time extensions) when delays are specifically caused by actions or inactions of a public entity, balancing risk between government and private contractors and possibly leading to more competitive bidding.

  2. Defines and limits eligible claims. By carefully specifying what kinds of delays qualify—such as failure to coordinate, lengthy stop work orders, or significant site unavailability—the bill aims to prevent frivolous claims while ensuring contractors are fairly compensated for serious, documentable public agency-caused delays.

  3. Imposes strict notice and documentation requirements. Contractors must provide prompt, detailed written notice and thorough cost records, with failure to do so resulting in loss of the claim. This incentivizes transparency and accurate record-keeping, and protects public entities from vague or late claims.

  4. Potential impact on project management and costs. Public entities may need to improve internal processes to avoid costly delays, while contractors may gain more confidence in pursuing public work, but the law could also increase the complexity and administrative burden of public contracts, possibly influencing overall project costs and timelines.

The daily · weekday mornings

Albany, before your first meeting.

Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.

Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.

Who cares

  • Public works contractors

    The bill would require contract clauses allowing claims for additional costs from specified public-entity-caused delays, subject to written notice within 15 days of learning the facts underlying the claim.

  • Subcontractors and material suppliers

    They could seek qualifying delay costs but would waive claims if they failed to provide required written notice or maintain and furnish cost records.

  • State agencies, municipalities and public authorities

    They would have to include delay-claim clauses in public works contracts and acknowledge claim notices in writing within five days.

  • School districts and special districts

    Their public works contracts would also be covered, exposing them to claims for specified delays such as prolonged site unavailability or stop-work orders affecting substantial work for more than 30 days.

Headline styles

Let Contractors Sue for Delays

Plain English, a few words. Used as the page title.

Sponsors

Primary sponsor
Michael H. Ranzenhofer

Senator · Senate District 61

Chair, Corporations, Authorities And Commissions

1 Co-sponsor

History

  1. Vetoed memo.355
  2. Delivered to governor
  3. Returned to senate
  4. Passed assembly
  5. Ordered to third reading cal.953
  6. Substituted for A7945A
  7. Referred to ways and means
  8. Delivered to assembly
  9. Passed senateVote 59–0
  10. Advanced to third reading
  11. 2nd report cal.
  12. 1st report cal.1105
Show 8 earlier actions
  1. Referred to finance
  2. Returned to senate
  3. Died in assembly
  4. Referred to ways and means
  5. Delivered to assembly
  6. Passed senateVote 63–0
  7. Ordered to third reading cal.2085
  8. Referred to rules

Companion bill

The same bill in the other chamber. A bill becomes law when one version passes both houses and the governor signs it, so either number can carry it.

A7945Assembly

Let Contractors Sue for Delays

Assembly Floor Calendar · Sponsor Ron Kim

Impact 6 · Moderate0% to pass

Full text

3 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗

STATE OF NEW YORK

6686

2017-2018 Regular Sessions

IN SENATE

June 13, 2017

Introduced by Sen. RANZENHOFER -- read twice and ordered printed, and when printed to be committed to the Committee on Rules

AN ACT to amend the state finance law, in relation to damages to contracts occasioned by delay

The People of the State of New York, represented in Senate and Assembly, do enact as follows:

Section 1. The state finance law is amended by adding a new section 138-b to read as follows:

§ 138-b. Damages occasioned by delay. 1. For purposes of this section the following terms shall have the following meanings:

(a) "Public entity" shall mean any state agency, department, board, bureau, municipal corporation, public benefit corporation, public authority or any other state entity, any school district or any other special district, or any instrumentality of the state or a political subdivision of the state.

(b) "Contract" shall mean any agreement awarded by a public entity for the design, construction, reconstruction, demolition, alteration, repair or improvement of any public works.

(c) "Delay" shall mean any delay, disruption, interference, inefficiencies, impedance, hindrance or acceleration in the performance of the contract which causes damages to be incurred by a contractor, subcontractor or materialman to a contract and which is a direct result of the act or omission of the public entity for whom the contractor, subcontractor or materialman is providing services as provided for in the contract.

(d) "Claim" shall mean a request for additional costs from the following causes listed in this subdivision attributable to delay in the performance of a contract, occasioned by any act or omission to act by the public entity with whom a contractor, subcontractor or materialman has contracted with, but shall not include delay from any other cause,

EXPLANATION--Matter in italics (underscored) is new; matter in brackets

[ ] is old law to be omitted.

LBD05191-05-7

S. 6686 2

which delay shall be compensated for solely by an extension of time to complete the performance of the work:

(i) the failure of the public entity to take reasonable measures to coordinate and progress the work;

(ii) extended delays attributable to the public entity in the review or issuance of orders-on-contract or field orders, in shop drawing reviews and approvals or as a result of the cumulative impact of multiple orders on contract, which constitute a qualitative change to the project work and which have a verifiable impact on project costs;

(iii) the unavailability of the site for such an extended period of time which significantly affects the scheduled completion of the contract; or

(iv) the issuance of a stop work order relative to a substantial portion of work for a period exceeding thirty days.

2. All contracts made and awarded shall contain a clause which allows a contractor, subcontractor or materialman to make a claim for additional costs arising from delay if such delay in the performance of the contract is caused by or occasioned by any act or omission of the entity with whom they have contracted in the contract, or any of such entity's representatives or agents.

3. The contractor, subcontractor or materialman shall provide a notice of claim of an anticipated claim for delay to a public entity by personal service or certified mail no more than fifteen days after such contractor knew the facts which form the basis of the claim. The public entity shall acknowledge receipt of the notice, in writing, within five days. Such notice shall at a minimum provide a description of any operations that were, are being or will be delayed, and the date or dates and reasons for the delay. In no case shall oral notice constitute notice pursuant to this section or be deemed to constitute a waiver of the written notice requirement. For the purposes of this section, failure to provide such notice shall be considered to have prejudiced the public entity.

4. Failure by a contractor to adequately progress the completion of work shall be considered in determining the causes of delay. For any claim asserted pursuant to this title, the contractor, subcontractor or materialman shall keep detailed written records of the costs and shall make them available for the purposes of audit and review. Failure to provide the required written notice or to maintain and furnish records of the costs of such claims shall constitute a waiver of the claim.

5. The following information shall be provided by the contractor upon request of a public entity if not previously supplied:

(a) a description of the operations that were delayed, the reasons for the delay and an explanation of how they were delayed;

(b) a detailed factual statement of the claim providing all necessary dates, locations and items of work affected by the claim;

(c) the date on which actions resulting in the claim occurred or conditions resulting in the claim became evident;

(d) the names, functions and activities of each contractor, subcontractor and materialman involved in, or knowledgeable about facts that gave rise to such claim;

(e) the identification of any pertinent documents, and the substance of any material oral communication relating to such claim;

(f) the amount of additional compensation sought; and

(g) if an extension of time is also requested, the specific number of days for which it is sought and the basis for such request as determined by an analysis of the construction progress schedule.

S. 6686 3

6. When submitting any claim, the contractor, subcontractor or materialman shall certify in writing and under oath that the supporting data is accurate and complete to his or her best knowledge or belief, and that any amount demanded reflects, in good faith, what he or she believes to be the public entity's liability.

§ 2. This act shall take effect on the one hundred eightieth day after it shall have become a law and shall apply to all contracts entered into on and after such date.

Reflowed for reading: line numbers and page breaks removed. Cite the official text.

Sponsor's memo

Title of bill

An act to amend the state finance law, in relation to damages to contracts occasioned by delay

Purpose or general idea of bill

Requires public contracts to include a clause authorizing contractors to recover damages for delay for itself as well as on behalf of subcontractors or materialmen.

Summary of specific provisions

Section 1 of this bill amends the State Finance Law by adding a new Section 138-b which would provide that all public works contracts shall contain a clause which allows a contractor, subcontractor, or materialman to make claim for additional costs due to excusable delays which are the result of actions or omissions by a public owner or any of its representatives. The act or omission must be within the scope of their responsibility or control.

Section 2 of the bill sets forth the effective date.

Justification

Current case law in New York State follows KALISCH-JARCHO, INC. V. CITY OF NEW YORK (578 NY 2nd 377) and subsequent court decisions, which allow a contractor to recover damages for such delay caused where the owner acted in bad faith and with deliberate intent, along with several other limited exceptions. In fact, the burden of proof to establish bad faith and deliberate intent makes it unlikely that contractors would be able to recover damages for delay.

Several public agencies, most notably NYS Office of General Services (OGS) and the federal government, have already recognized the unfairness of this restriction and have provided in their public contracts for a more equitable allowance for damages for delays resulting from public agency action.

By tracking current OGS contract language, this bill would reinstate the pre-Kalisch-Jarcho standard making "no damages for delay" clauses unenforceable where the contractor has suffered a delay for an unreasonable time and such delay is the fault or responsibility of the project owner. It would require all public contracts to include a clause authorizing contractors to recover damages for delay under such circumstances, which is both fair and equitable, and recognized as such by one of the largest agencies in New York State.

Seventeen states allow for the specific recovery of damages related to expenses incurred by the contractor for a delay for which the state governmental unit is responsible, which was unreasonable under the circumstances, and which was not within the contemplation of the parties to the contract. Many more states recognize a common law right to damages for delay. New York should not be an exception to this trend.

In 1998, Governor Pataki vetoed S.6711-B, a more generalized proposal to achieve the same relief sought by this legislation. In his veto message (see Veto Message 1404), Governor Pataki stated that he was sympathetic to the concept and that he recognized that policy of OGS was directed to address the needs sought in the legislation, but there were technical problems in the bill draft. This bill addresses the technical issues raised by Governor Pataki and clarifies liability for damages where actions or omissions of a public agency are directly associated with the damages incurred by a covered contractor.

Prior legislative history

New bill.

Fiscal implications

To be determined.

Effective date

This act shall take effect 180 days after enactment.