A3520Assembly2021-2022 Session

Let Contractors Claim Delay Costs

Official title

“Relates to damages to contracts occasioned by delay”

Sponsor Ron KimAD-40
Status
In Assembly Committee
Governmental Operations
Impact
6/10
Moderate
Passage
0%

Bill progress

Step 2 of 7

In committee · Governmental Operations

What's happening

This bill requires New York state agency contracts to allow contractors to claim additional costs for delays caused by the agency.

Why it matters

  1. Increases contractor protection against agency-caused delays. By defining what counts as a delay and specifying that contractors can claim additional costs, the bill provides clearer recourse for businesses affected by poor agency planning, slow approvals, or inaccessible work sites.

  2. Requires documentation and timely claims. Contractors must provide detailed written notice and supporting records within strict deadlines, ensuring both parties address delay-related disputes quickly and based on evidence, which could help reduce litigation and project standstills.

  3. Promotes accountability for state agencies. The bill obliges agencies to acknowledge claims promptly and may motivate them to better coordinate and manage projects, potentially reducing costly delays and inefficiencies in public works.

  4. Standardizes public works contract terms. By mandating these delay claim provisions in all state contracts, the law would create more predictable and fair conditions for contractors bidding on government projects, possibly encouraging more competition and better value for the state.

The daily · weekday mornings

Albany, before your first meeting.

Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.

Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.

Who cares

  • Public works contractors

    The bill would require state contracts to allow claims for additional costs from specified delays caused by a state agency’s material act or omission.

  • State agencies and public authorities

    They would have to include delay-claim clauses in covered contracts and acknowledge contractors’ written notices within five days.

  • Public works design firms

    Covered design contracts would carry delay-claim rights, but firms would risk waiving claims if they miss the 15-day written notice deadline or fail to maintain and furnish cost records.

Headline styles

Let Contractors Claim Delay Costs

Plain English, a few words. Used as the page title.

Sponsors

Primary sponsor
Ron Kim

Assembly Member · Assembly District 40

Chair, Tourism, Parks, Arts and Sports Development

No co-sponsors yet.

History

  1. Referred to governmental operations
  2. Referred to governmental operations

Full text

2 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗

STATE OF NEW YORK

3520

2021-2022 Regular Sessions

IN ASSEMBLY

January 27, 2021

Introduced by M. of A. KIM -- read once and referred to the Committee on Governmental Operations

AN ACT to amend the state finance law, in relation to damages to contracts occasioned by delay

The People of the State of New York, represented in Senate and Assembly, do enact as follows:

Section 1. The state finance law is amended by adding a new section 138-b to read as follows:

§ 138-b. Damages occasioned by delay. 1. For purposes of this section the following terms shall have the following meanings:

(a) "State agency" shall mean all entities as defined in section one hundred seventy-nine-e of this chapter and subdivision one of section two of the public authorities law.

(b) "Contract" shall mean any agreement awarded by a state agency for the design, construction, reconstruction, demolition, alteration, repair or improvement of any public works project.

(c) "Delay" shall mean any delay, disruption, interference, inefficiencies, impedance, hindrance or acceleration in the performance of the contract which causes damages to be incurred by a contractor.

(d) "Claim" shall mean a request for additional costs only from the following causes:

(i) the failure of the state agency to take reasonable measures to coordinate and progress the work;

(ii) extended delays attributable to the state agency in the review or issuance of orders-on-contract or field orders, in shop drawing reviews and approvals or as a result of the cumulative impact of multiple orders on contract, which constitute a qualitative change to the project work and which have a verifiable impact on project costs; or

(iii) the unavailability of the site for such an extended period of time which significantly affects the scheduled completion of the contract.

EXPLANATION--Matter in italics (underscored) is new; matter in brackets

[ ] is old law to be omitted.

LBD06065-01-1

A. 3520 2

2. All contracts made and awarded shall contain a clause which allows a contractor to make a claim for additional costs arising from delay in the performance of a contract if such delay is caused by a material act or omission of the state agency.

3. The contractor shall provide a notice of claim of an anticipated claim for delay to a state agency by personal service or certified mail no more than fifteen days after such contractor knew the facts which form the basis of the claim. The state agency shall acknowledge receipt of the notice, in writing, within five days. Such notice shall at a minimum provide a description of any operations that were, are being or will be delayed, and the date or dates and reasons for the delay. In no case shall oral notice constitute notice pursuant to this section or be deemed to constitute a waiver of the written notice requirement. For the purposes of this section, failure to provide such notice shall be considered to have prejudiced the state agency.

4. Failure by a contractor to adequately progress the completion of work shall be considered in determining the causes of delay. For any claim asserted pursuant to this title, the contractor shall keep detailed written records of the costs and shall make them available for the purposes of audit and review. Failure to provide the required written notice or to maintain and furnish records of the costs of such claims shall constitute a waiver of the claim.

5. The following information shall be provided by the contractor upon request of a state agency if not previously supplied:

(a) a description of the operations that were delayed, the reasons for the delay and an explanation of how they were delayed;

(b) a detailed factual statement of the claim providing all necessary dates, locations and items of work affected by the claim;

(c) the date on which actions resulting in the claim occurred or conditions resulting in the claim became evident;

(d) the names, functions and activities of each contractor involved in, or knowledgeable about facts that gave rise to such claim;

(e) the identification of any pertinent documents, and the substance of any material oral communication relating to such claim;

(f) the amount of additional compensation sought; and

(g) if an extension of time is also requested, the specific number of days for which it is sought and the basis for such request as determined by an analysis of the construction progress schedule.

6. When submitting any claim, the contractor shall certify in writing and under oath that the supporting data is accurate and complete to his or her best knowledge or belief, and that any amount demanded reflects, in good faith, what he or she believes to be the state agency's liability.

§ 2. This act shall take effect on the one hundred eightieth day after it shall have become a law and shall apply to all contracts entered into on and after such date.