What's happening
This bill requires public owners, instead of contractors, to pay subcontractors directly for work on public construction projects.
Why it matters
Shifts financial risk from subcontractors to public owners. By having public owners pay subcontractors directly, this bill aims to reduce the risk that subcontractors will face delayed or withheld payments if the main contractor becomes insolvent or fails to pay.
Increases public owner oversight and administrative responsibility. Public agencies will need to track and process payment requisitions from both contractors and subcontractors, potentially creating new administrative burdens and accountability for accurate, timely payments and dispute resolution.
Alters cash flow and retainage practices. The bill sets clear limits (generally 5%, with some exceptions up to 10%) on how much public owners can retain from both contractors and subcontractors, which may help subcontractors maintain healthier cash flow and reduce their financial vulnerability during projects.
Clarifies scope to first-tier subcontractors only. The new process only applies to subcontractors who contract directly with the main contractor, not to lower-tier subs, which means some payment flow risks and complications remain for those further down the subcontracting chain.
Albany, before your first meeting.
Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.
Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.
Headline styles
Direct Pay for Subcontractors
Plain English, a few words. Used as the page title.
Sponsors
History
- Referred to governmental operations
- Referred to governmental operations
Full text
8 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗
STATE OF NEW YORK
6824
2021-2022 Regular Sessions
IN ASSEMBLY
April 8, 2021
Introduced by M. of A. BICHOTTE HERMELYN, HYNDMAN, SEAWRIGHT, WALKER, SOLAGES -- read once and referred to the Committee on Governmental Operations
AN ACT to amend the state finance law and the general municipal law, in relation to payment by public owners to contractors and subcontractors
The People of the State of New York, represented in Senate and Assembly, do enact as follows:
Section 1. The opening paragraph and subdivisions 1 and 2 of section 139-f of the state finance law, the opening paragraph as added by chapter 769 of the laws of 1978, subdivision 1 as amended by chapter 341 or the laws of 2020 and subdivision 2 as amended by section 16 of part MM of chapter 57 of the laws of 2008, are amended to read as follows:
Notwithstanding the provisions of any other law to the contrary, except the provisions of section thirty-eight of the highway law, all contracts made and awarded by the state, or by any public department, or by any public benefit corporation or by any public corporation or official thereof, hereafter referred to as the public owner, for construction, reconstruction or alteration of any public work project shall provide for payment by the public owner to the contractor and [payment by the contractor] to the subcontractor or subcontractors in accordance with the following:
1. Payment by public owners to contractors. The contractor shall periodically, in accordance with the terms of the contract, submit to the public owner and/or his agent a requisition for a progress payment for the work performed and/or materials furnished to the date of the requisition by the contractor and all subcontractors, less any amount previously paid to the contractor or subcontractors. The public owner shall in accordance with the terms of the contract approve and promptly pay the requisition for the progress payment less an amount necessary to satisfy any claims, liens or judgments against the contractor or subcontractors which have not been suitably discharged and less any retained
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD06229-01-1
A. 6824 2
amount as hereafter described. The public owner shall retain not more than five per centum of each progress payment to the contractor and subcontractors except that the public owner may retain in excess of five per centum but not more than ten per centum of each progress payment to the contractor provided that there are no requirements by the public owner for the contractor to provide a performance bond and a labor and material bond both in the full amount of the contract. The public owner shall pay, upon requisition from the contractor, for materials pertinent to the project which have been delivered to the site or off-site by the contractor [and/or subcontractor] and suitably stored and secured as required by the public owner and the contractor provided, the public owner may limit such payment to materials in short and/or critical supply and materials specially fabricated for the project each as defined in the contract, including balances owed to subcontractors. When the work or major portions thereof as contemplated by the terms of the contract has reached substantial completion which, for the purposes of this section, shall mean the state in the progress of the project when the work required by the contract with the public owner is sufficiently complete in accordance with the contract so that the public owner may occupy or utilize the work for its intended use; provided further, that "substantial completion" shall apply to the entire project or a portion of the entire project if the contract with the public owner provides for occupancy or use of a portion of the project, the contractor shall submit to the public owner and/or his agent a requisition for payment of the remaining amount of the contract balance. Upon receipt of such requisition the public owner shall approve and promptly pay the remaining amount of the contract balance less two times the value of any remaining items to be completed and an amount necessary to satisfy any claims, liens or judgments against the contractor which have not been suitably discharged. As the remaining items of work are satisfactorily completed or corrected, the public owner shall promptly pay, upon receipt of a requisition, for these remaining items less an amount necessary to satisfy any claims, liens or judgments against the contractor which have not been suitably discharged. Any claims, liens and judgments referred to in this section shall pertain to the project and shall be filed in accordance with the terms of the applicable contract and/or applicable laws.
2. Payment by [contractors] public owners to subcontractors. [Within seven calendar days of the receipt] (a) Each subcontractor shall periodically, in accordance with the terms of the contract, submit to the public owner and/or his agent and to the contractor and/or his agent a requisition for a progress payment for the work performed and/or materials furnished to the date of the requisition, less any amount previously paid to the contractor. At the time of any payment [from] by the public owner[,] to the contractor as provided in subdivision one of this section, the public owner shall pay each of [his] the subcontractors and materialmen the proceeds from the payment representing the value of the work performed and/or materials furnished by the subcontractor and/or materialman and reflecting the percentage of the subcontractor's work completed or the materialman's material supplied in the requisition approved by the owner and based upon the actual value of the subcontract or purchase order less an amount necessary to satisfy any claims, liens or judgments against the subcontractor or materialman which have not been suitably discharged and less any retained amount as hereafter described. [Failure by the contractor to pay any subcontractor or materialman within seven calendar days of the receipt of any payment from the
A. 6824 3
public owner shall result in the commencement and accrual of interest on amounts due to such subcontractor or materialman for the period beginning on the day immediately following the expiration of such seven calendar day period and ending on the date on which payment is made by the contractor to such subcontractor or materialman. Such interest payment shall be the sole responsibility of the contractor, and shall be paid at the rate of interest in effect on the date payment is made by the contractor. Notwithstanding any other provision of law to the contrary, interest shall be computed at the rate established in paragraph (b) of subdivision one of section seven hundred fifty-six-b of the general business law. The contractor shall retain not more than five per centum of each payment to the subcontractor and/or materialman except that the contractor may retain in excess of five per centum but not more than ten per centum of each payment to the subcontractor provided that prior to entering into a subcontract with the contractor, the subcontractor is unable or unwilling to provide a performance bond and a labor and material bond, both in the full amount of the subcontract, at the request of the contractor. However, the contractor shall retain nothing from those payments representing proceeds owed the subcontractor and/or materialman from the public owner's payments to the contractor for the remaining amounts of the contract balance as provided in subdivision one of this section. If the contractor has failed to submit a requisition for payment of the remaining amounts of the contract balance within ninety days of substantial completion as provided in subdivision one of this section, then any clause in the subcontract between the contractor and the subcontractor or materialman which states that payment by the contractor to such subcontractor or materialman is contingent upon payment by the owner to the contractor shall be deemed invalid. Within seven calendar days of the receipt of payment from the contractor, the subcontractor and/or materialman shall pay each of his subcontractors and materialmen in the same manner as the contractor has paid the subcontractor, including interest as herein provided above. Nothing provided herein shall create any obligation on the part of the public owner to pay or to see to the payment of any moneys to any subcontractor or materialman from any contractor nor shall anything provided herein serve to create any relationship in contract or otherwise, implied or expressed, between the subcontractor or materialman and the public owner.] The public owner shall retain not more than five per centum of each progress payment to the subcontractor except that the public owner may retain in excess of five per centum but not more than ten per centum of each progress payment to the subcontractor provided that there are no requirements by the public owner for the subcontractor to provide a performance bond and a labor and material bond both in the full amount of the contract. The public owner shall pay, upon requisition from the contractor as provided in subdivision one of this section, for materials pertinent to the project which have been delivered to the site or offsite by the subcontractor and suitably stored and secured as required by the public owner and the subcontractor provided, the public owner may limit such payment to materials in short and/or critical supply and materials specially fabricated for the project each as defined in the contract. When the work or major portions thereof as contemplated by the terms of the contract are substantially completed, the subcontractor shall submit to the contractor and/or his or her agent a requisition for payment of the remaining amount of the contract balance. The contractor shall submit a contract requisition containing all requisitions from subcontractors to the public owner. Upon receipt of such requisition the
A. 6824 4
public owner shall approve and promptly pay the remaining amount of the contract balance less two times the value of any remaining items to be completed and an amount necessary to satisfy any claims, liens or judgments against the subcontractor which have not been suitably discharged. As the remaining items of work are satisfactorily completed or corrected, the public owner shall promptly pay, upon receipt of a requisition, for these remaining items less an amount necessary to satisfy any claims, liens or judgments against the subcontractor which have not been suitably discharged. Any claims, liens and judgments referred to in this section shall pertain to the project and shall be filed in accordance with the terms of the applicable contract and/or applicable laws.
(b) As used in this section, "subcontractor" means only those subcontractors that report directly to the main contractor with whom the public owner has entered into the contract, and does not include subcontractors of subcontractors.
§ 2. The opening paragraph and subdivisions 1 and 2 of section 106-b of the general municipal law, the opening paragraph as amended by chapter 661 of the laws of 1992, subdivision 1 as amended by chapter 341 or the laws of 2020, and subdivision 2 as amended by section 15 of part MM of chapter 57 of the laws of 2008, are amended to read as follows:
Notwithstanding the provisions of any other law to the contrary, all contracts made and awarded by the appropriate officer, board or agency of a political subdivision or of any district therein, hereafter referred to as the public owner, for construction, reconstruction or alteration of any public work project shall provide for payment by the public owner to the contractor and [payment by the contractor] to the subcontractor or subcontractors in accordance with the following:
1. Payment by public owners to contractors. (a) The contractor shall periodically, in accordance with the terms of the contract, submit to the public owner and/or his agent a requisition for a progress payment for the work performed and/or materials furnished to the date of the requisition by the contractor and all subcontractors less any amount previously paid to the contractor or subcontractors. The public owner shall in accordance with the terms of the contract approve and promptly pay the requisition for the progress payment less an amount necessary to satisfy any claims, liens or judgments against the contractor or subcontractors which have not been suitably discharged and less any retained amount as hereafter described. The public owner shall retain not more than five per centum of each progress payment to the contractor or subcontractors except that the public owner may retain in excess of five per centum but not more than ten per centum of each progress payment to the contractor provided that there are no requirements by the public owner for the contractor to provide a performance bond and a labor and material bond both in the full amount of the contract. The public owner shall pay, upon requisition from the contractor, for materials pertinent to the project which have been delivered to the site or off-site by the contractor [and/or subcontractor] and suitably stored and secured as required by the public owner and the contractor provided, the public owner may limit such payment to materials in short and/or critical supply and materials specially fabricated for the project each as defined in the contract. When the work or major portions thereof as contemplated by the terms of the contract has reached substantial completion which, for the purposes of this section, shall mean, for public owners other than school districts and boards of cooperative educational services, the state in the progress of the project when the work required by the contract with the public owner is sufficiently
A. 6824 5
Reflowed for reading: line numbers and page breaks removed. Cite the official text.
Summaries, headlines and scores are AI-generated from the official bill text. How we score bills. Source: NYS Open Legislation.