This bill limits construction contract retainage to no more than 5% and allows final invoicing at substantial completion.
Why it matters
Caps retainage at 5%. By limiting retainage to a maximum of 5% of the contract value, the bill reduces the amount of money that can be withheld from contractors and subcontractors, improving cash flow for construction businesses and potentially reducing financial strain, especially for smaller firms.
Allows earlier final payments. Permitting contractors to submit a final invoice at “substantial completion” (rather than after all obligations are fully met) can speed up payment timelines, helping contractors cover costs and move on to new projects sooner.
Aligns subcontractor retainage with owner’s rate. The bill ensures that subcontractors cannot have more withheld from them than the owner is withholding from the general contractor, promoting fairness and consistency throughout the payment chain.
Imposes penalties for late retainage release. By instituting a 1% per month interest penalty for late release of retainage, the bill creates a strong incentive for timely payment, which may deter payment delays and improve trust and predictability in the construction sector.
Albany, before your first meeting.
Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.
Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.
Who cares
Construction contractors
The bill would let them submit a final invoice for payment in full at substantial completion rather than after performing all contractual obligations.
Construction project owners
The bill would cap the retainage they may hold by mutual agreement at five percent of the contract sum.
Construction subcontractors
The bill would cap retainage withheld by contractors and subcontractors at five percent and prohibit it from exceeding the percentage retained by the owner.
Headline styles
Cap Construction Retainage at 5%
Plain English, a few words. Used as the page title.
Sponsors
History
- Referred to economic development
- Print number 6985b
- Amend and recommit to economic development
- Print number 6985a
- Amend and recommit to economic development
- Referred to economic development
Companion bill
The same bill in the other chamber. A bill becomes law when one version passes both houses and the governor signs it, so either number can carry it.
Limit Construction Payment Delays
In Senate Committee · Consumer Protection · Sponsor Neil D. Breslin
Full text
2 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗
STATE OF NEW YORK
6985--B
2021-2022 Regular Sessions
IN ASSEMBLY
April 19, 2021
Introduced by M. of A. CUSICK, STIRPE, ZINERMAN -- read once and referred to the Committee on Economic Development -- committee discharged, bill amended, ordered reprinted as amended and recommitted to said committee -- committee discharged, bill amended, ordered reprinted as amended and recommitted to said committee
AN ACT to amend the general business law, in relation to payment and retainage in construction contracts
The People of the State of New York, represented in Senate and Assembly, do enact as follows:
Section 1. The opening paragraph of paragraph (a) of subdivision 2 of section 756-a of the general business law, as amended by chapter 417 of the laws of 2009, is amended to read as follows:
A contractor shall be entitled to invoice the owner for interim payments at the end of the billing cycle. A contractor shall be entitled to submit a final invoice for payment in full [upon the performance of all the contractor's obligation under the contract] upon reaching substantial completion, as such term is defined in the contract or as it is contemplated by the terms of the contract.
§ 2. Section 756-c of the general business law, as added by chapter 127 of the laws of 2002, is amended to read as follows:
§ 756-c. Retention. By mutual agreement of the relevant parties an owner may retain [a reasonable amount] no more than five per centum of the contract sum as retainage. A contractor or subcontractor may also retain [a reasonable amount] no more than five per centum for retainage [so long as the amount does not] and in no case shall retainage exceed the actual percentage retained by the owner. Retainage shall be released by the owner to the contractor no later than thirty days after the final approval of the work under a construction contract. In the event that an owner fails to release retainage as required by this article, or the contractor or subcontractor fails to release a proportionate amount of retainage to the relevant parties after receipt of retainage from the
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD01144-06-1
A. 6985--B 2
owner, the owner, contractor, or subcontractor, as the case may be, shall be subject to the payment of interest at the rate of one percent per month on the date retention was due and owing.
§ 3. This act shall take effect immediately and shall apply to contracts entered into on or after such effective date.