What's happening
This bill requires state contracts to include provisions for contractors to claim additional costs if project delays are caused by state agencies.
Why it matters
Makes state agencies more accountable for project delays. By explicitly allowing contractors to claim extra costs if delays are caused by the state's own actions or inactions, agencies are incentivized to better coordinate and manage public works projects.
Sets clear requirements for contractor claims. Contractors must provide prompt written notice (within 15 days) and maintain detailed records to qualify for compensation, which encourages thorough documentation and helps prevent frivolous or poorly substantiated claims.
Limits compensation to specific types of agency-caused delays. Only certain delays—like failure to coordinate work, slow approvals that impact costs, or site unavailability—are covered, narrowing the scope and potentially reducing disputes over what delays are eligible.
Could affect project costs and timelines. Contractors might bid more accurately and be less likely to inflate prices to cover potential state-caused delays, but the state could also face increased financial liability and administrative workload to process and audit these claims.
Albany, before your first meeting.
Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.
Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.
Headline styles
Let Contractors Claim Delay Damages
Plain English, a few words. Used as the page title.
Sponsors
Senator · Senate District 14
No co-sponsors yet.
History
- Referred to procurement and contracts
- Referred to rules
Full text
2 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗
STATE OF NEW YORK
7166
2021-2022 Regular Sessions
IN SENATE
June 4, 2021
Introduced by Sen. COMRIE -- read twice and ordered printed, and when printed to be committed to the Committee on Rules
AN ACT to amend the state finance law, in relation to damages to contracts occasioned by delay
The People of the State of New York, represented in Senate and Assembly, do enact as follows:
Section 1. The state finance law is amended by adding a new section 138-b to read as follows:
§ 138-b. Damages occasioned by delay. 1. For purposes of this section the following terms shall have the following meanings:
(a) "State agency" shall mean any state department, board, bureau, commission, division, office, council, or state committee or any state authority as defined in subdivision one of section two of the public authorities law. Such term shall not include the legislature or judiciary.
(b) "Contract" shall mean any agreement awarded by a state agency for the design, construction, reconstruction, demolition, alteration, repair or improvement of any public works project.
(c) "Delay" shall mean any delay, disruption, interference, inefficiencies, impedance, hindrance or acceleration in the performance of the contract which causes damages to be incurred by a contractor.
(d) "Claim" shall mean a request for additional costs only from the following causes:
(i) the failure of the state agency to take reasonable measures to coordinate and progress the work;
(ii) extended delays attributable to the state agency in the review or issuance of orders-on-contract or field orders, in shop drawing reviews and approvals or as a result of the cumulative impact of multiple orders on contract, which constitute a qualitative change to the project work and which have a verifiable impact on project costs; or
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD06065-02-1
S. 7166 2
(iii) the unavailability of the site for such an extended period of time which significantly affects the scheduled completion of the contract.
2. All contracts made and awarded shall contain a clause which allows a contractor to make a claim for additional costs arising from delay in the performance of a contract if such delay is caused by a material act or omission of the state agency.
3. The contractor shall provide a notice of claim of an anticipated claim for delay to a state agency by personal service or certified mail no more than fifteen days after such contractor knew the facts which form the basis of the claim. The state agency shall acknowledge receipt of the notice, in writing, within five days. Such notice shall at a minimum provide a description of any operations that were, are being or will be delayed, and the date or dates and reasons for the delay. In no case shall oral notice constitute notice pursuant to this section or be deemed to constitute a waiver of the written notice requirement. For the purposes of this section, failure to provide such notice shall be considered to have prejudiced the state agency.
4. Failure by a contractor to adequately progress the completion of work shall be considered in determining the causes of delay. For any claim asserted pursuant to this title, the contractor shall keep detailed written records of the costs and shall make them available for the purposes of audit and review. Failure to provide the required written notice or to maintain and furnish records of the costs of such claims shall constitute a waiver of the claim.
5. The following information shall be provided by the contractor upon request of a state agency if not previously supplied:
(a) a description of the operations that were delayed, the reasons for the delay and an explanation of how they were delayed;
(b) a detailed factual statement of the claim providing all necessary dates, locations and items of work affected by the claim;
(c) the date on which actions resulting in the claim occurred or conditions resulting in the claim became evident;
(d) the names, functions and activities of each contractor involved in, or knowledgeable about facts that gave rise to such claim;
(e) the identification of any pertinent documents, and the substance of any material oral communication relating to such claim;
(f) the amount of additional compensation sought; and
(g) if an extension of time is also requested, the specific number of days for which it is sought and the basis for such request as determined by an analysis of the construction progress schedule.
6. When submitting any claim, the contractor shall certify in writing and under oath that the supporting data is accurate and complete to his or her best knowledge or belief, and that any amount demanded reflects, in good faith, what he or she believes to be the state agency's liability.
§ 2. This act shall take effect on the one hundred eightieth day after it shall have become a law and shall apply to all contracts entered into on and after such date.
Reflowed for reading: line numbers and page breaks removed. Cite the official text.
Sponsor's memo
Title of bill
An act to amend the state finance law, in relation to damages to contracts occasioned by delay
Purpose or general idea of bill
Requires state agency and authority public works contracts to include a clause authorizing contractors to recover reasonable damages for delay under limited circumstances.
Summary of specific provisions
Section 1 of this bill amends the State Finance Law by adding a new Section 138-b which would provide that all state agency and state authority contracts shall contain a clause which allows a contractor to make claim for additional costs due to excusable delays which are the result of actions or omissions by a state agency or authority. The act or omission must be within the scope of their responsibility or control. Section 2 of the bill sets forth the effective date.
Read the full memo (610 words)
Justification
Current case law in New York State follows KALISCH-JARCHO, INC. V. CITY OF NEW YORK (578 NY 2nd 377) and subsequent Court of Appeals decisions, which allow a contractor to recover damages for such delay caused where the owner acted in bad faith and with deliberate intent, along with several other limited exceptions. In fact, the burden of proof to estab- lish bad faith and deliberate intent makes it unlikely that contractors would be able to recover damages for delay. Several public agencies, most notably NYS Office of General Services (OGS) and the federal government, have already recognized the unfairness of this. restriction and have provided in their public contracts for a more equitable allow- ance for damages for delays resulting from public agency action. By tracking current OGS contract language, this bill would reinstate the pre-Kalisch-Jarcho standard making "no damages for delay" clauses unen- forceable where the contractor has suffered a delay for an unreasonable time and such delay is the fault or responsibility of the state agency. It would require state agency and authority contracts to include a clause authorizing contractors to recover damages for delay under such circumstances, which is both fair and equitable, and recognized as such by one of the largest agencies in New York State. Over 17 states allow for the specific recovery of damages related to expenses incurred by the contractor for a delay for which the state governmental unit is respon- sible, and which delay was unreasonable under the circumstances, and was not within the contemplation of the parties to the contract. Many more states recognize a common law right to damages for delay. New York should not be an exception to this trend, based on simple principles of equity and fairness.
In 2018, Governor Cuomo vetoed a more expansive version of this legis- lation (S.6686/A.7945-A). In his veto message (see Veto Message 355-2018), Governor Cuomo raised several technical issues of concern. This bill addresses the technical issues raised by Governor Cuomo and clarifies liability for damages where actions or omissions of a state agency or state authority are directly associated with the damages incurred by a covered contractor. Specifically and in response to the Governor's concerns, this bill a) is limited in application and scope only to state agencies and state authorities; b) removes prior language that the Governor was concerned could establish privity of contract between a subcontractor and a public agency, and other third parties; and c) further limits and narrows the criteria for a delay damages claim against a state agency.
Prior legislative history
New bill.
Fiscal implications
To be determined. However, a standardized "damages for delay" clause in state agency and authority contracts will result in decreased litigation costs to the state and contractors.
Effective date
This act shall take effect 180 days after enactment.