Skip to content
A4035Assembly2023-2024 SessionSame asS4415

Speed Up MTA Construction

Official title

“Expedites MTA capital project construction by establishing a process for utility relocation necessary for such construction”

Sponsor Zohran MamdaniAD-36+5 co-sponsorsAffects Economy
Status
In Assembly Committee
Corporations, Authorities And Commissions
Impact
6/10
Moderate
Passage
0%

Bill progress

Step 2 of 7

In committee · Corporations, Authorities And Commissions

What's happening

This bill streamlines utility relocation processes for MTA capital projects by establishing clear procedures and timelines for required work.

Why it matters

  1. Creates a standardized procedure for utility relocations during MTA projects, reducing opportunities for delays or disputes between the MTA and utility companies by setting clear responsibilities and timelines.

  2. Limits the ability of utility companies to delay projects by withholding design approvals or imposing additional requirements not related to current standards, ensuring that only necessary work within the affected area is required.

  3. Balances cost responsibilities by specifying that the MTA pays for work done by its contractors, while also allowing utilities to perform portions of the work on a schedule set by the MTA (with reasonable notice), helping to avoid drawn-out negotiations over who does what and when.

  4. Prevents utility companies from shifting the burden or creating additional relocation requirements for other utilities without MTA agreement, reducing the risk of cascading complications and project slowdowns.

The daily · weekday mornings

Albany, before your first meeting.

Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.

Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.

Who cares

  • Metropolitan Transportation Authority

    The bill would let the MTA or its contractors design necessary utility work for transportation projects and give the MTA authority to set reasonable schedules for utility-performed work after consultation.

  • Public service corporations

    Utilities would have to review and approve designs within 30 days or another reasonable period set by the MTA after consultation, and could not unreasonably withhold approval.

  • MTA construction contractors

    Contractors could prepare utility-work designs, with the MTA bearing the cost of all work performed by its own contractors.

  • Utilities seeking infrastructure upgrades

    Utilities could not require upgrades for anticipated service increases or other betterments without MTA agreement, except for compliance with current standards within the required work area.

Headline styles

Speed Up MTA Construction

Plain English, a few words. Used as the page title.

Sponsors

History

  1. Referred to corporations, authorities and commissions
  2. Referred to corporations, authorities and commissions

Companion bill

The same bill in the other chamber. A bill becomes law when one version passes both houses and the governor signs it, so either number can carry it.

S4415Senate

Speed Up MTA Projects

In Senate Committee · Transportation · Sponsor Leroy Comrie

Impact 7 · Significant0% to pass

Full text

2 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗

STATE OF NEW YORK

4035

2023-2024 Regular Sessions

IN ASSEMBLY

February 9, 2023

Introduced by M. of A. MAMDANI -- Multi-Sponsored by -- M. of A. CARROLL, FORREST, GALLAGHER, MITAYNES, RAGA, SEAWRIGHT, SEPTIMO, SHRESTHA, SIMONE -- read once and referred to the Committee on Corporations, Authorities and Commissions

AN ACT to amend the public authorities law, in relation to expediting metropolitan commuter transportation authority capital project construction by establishing a process for utility relocation necessary for such construction

The People of the State of New York, represented in Senate and Assembly, do enact as follows:

Section 1. Section 1266 of the public authorities law is amended by adding a new subdivision 12-b to read as follows:

12-b. For the purposes of this subdivision, the term "required work" shall mean any necessary removal, relocation, protection, or replacement of any pipes, mains, conduits or other infrastructure of any public service corporation and any fixtures and appliances connected therewith or attached thereto, either temporarily or permanently. Whenever the authority determines that any required work exists in connection with the improvement, construction, reconstruction, or rehabilitation of a transportation facility, all of the following provisions shall apply:

(a) The design for such required work shall be prepared by the authority or the authority's contractor. Such design shall be subject to the review and approval of the public service corporation, which shall not be unreasonably withheld. Such review and approval shall be completed within thirty days, or within such other reasonable period of time as may be determined by the authority after consultation with the public service corporation.

(b) In reviewing and approving designs for such required work, a public service corporation shall not create the need for another public service corporation to remove or relocate its pipes, mains, conduits or other infrastructure without the agreement of the authority.

EXPLANATION--Matter in italics (underscored) is new; matter in brackets

[ ] is old law to be omitted.

LBD06493-01-3

(c) In reviewing and approving designs for such required work, a public service corporation shall not require the authority to provide for anticipated future service increases or other betterments, other than to comply with current standards, without the authority's agreement. Betterments to comply with current standards shall only be required by the public service corporation within the area of such required work.

(d) The authority shall bear the cost of all work performed by its own contractors.

(e) Where the public service corporation determines that it shall perform any portion of such required work, such portion of such required work shall be performed according to a schedule determined by the authority after consultation with the public service corporation, provided that such schedule is reasonable and that the authority provides at least thirty days' notice.

§ 2. This act shall take effect immediately.

Reflowed for reading: line numbers and page breaks removed. Cite the official text.

Summaries, headlines and scores are AI-generated from the official bill text. How we score bills. Source: NYS Open Legislation.