What's happening
This bill allows New York utilities to use and be incentivized for advanced grid enhancement technologies to improve electric transmission efficiency and cost-effectiveness.
Why it matters
Accelerates grid modernization. by formally defining and supporting the adoption of cutting-edge technologies—like dynamic line ratings and advanced power flow controls—potentially speeding up how quickly utilities can integrate renewable energy and respond to new grid demands.
Incentivizes utility innovation. by allowing utilities to propose financial rewards for deploying cost-effective grid enhancement solutions, aligning utility profit motives with public goals for a more efficient and reliable electric grid.
Requires regular accountability and transparency. through mandated five-year reporting by utilities on the deployment of these technologies, providing oversight and data for policymakers and the public to track grid improvements and investment effectiveness.
Could reduce customer costs and improve system reliability. by encouraging the selection of the most cost-effective strategies—possibly lowering the need for expensive new transmission lines and making better use of existing infrastructure, which may result in lower rates or fewer outages for consumers.
Albany, before your first meeting.
Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.
Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.
Who cares
Electric utilities
The bill would let them propose financial incentives for cost-effective grid technology deployments and require deployment reports every five years beginning five years after the law takes effect.
Public Service Commission and Department of Public Service
The bill would give regulators a framework to evaluate and approve grid-enhancing technologies as alternatives or complements to other transmission investments.
New York Power Authority
The bill would authorize the authority to assess and deploy cost-effective grid-enhancing technologies when constructing or upgrading transmission facilities, subject to trustee determinations and any necessary commission approval.
Grid technology and advanced conductor suppliers
Their products could be considered in transmission investment analyses and approved for deployment when they offer a more cost-effective way to meet transmission goals.
Headline styles
Upgrade Electric Grid Technology
Plain English, a few words. Used as the page title.
Sponsors
1 Co-sponsor
History
- Tabled
- Vetoed memo.119
- Delivered to governor
- Returned to assembly
- Passed senateVote 58–2
- 3rd reading cal.1180
- Substituted for S7868A
- Referred to energy and telecommunications
- Delivered to senate
- Passed assembly
- Ordered to third reading rules cal.263
- Rules report cal.263
Show 5 earlier actions
- Reported
- Reported referred to rules
- Print number 9105a
- Amend (t) and recommit to energy
- Referred to energy
Companion bill
The same bill in the other chamber. A bill becomes law when one version passes both houses and the governor signs it, so either number can carry it.
Upgrade Electric Grid Tech
Senate Floor Calendar · Sponsor Rachel May
Full text
2 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗
STATE OF NEW YORK
9105--A
IN ASSEMBLY
February 7, 2024
Introduced by M. of A. ANDERSON -- read once and referred to the Committee on Energy -- committee discharged, bill amended, ordered reprinted as amended and recommitted to said committee
AN ACT to amend the public service law and the public authorities law, in relation to advancing grid enhancement technologies
The People of the State of New York, represented in Senate and Assembly, do enact as follows:
Section 1. The public service law is amended by adding a new section 66-x to read as follows:
§ 66-x. Advancing grid enhancement technologies. 1. For the purposes of this section, the following terms shall have the following meanings:
(a) "Grid enhancing technology" means any hardware or software technology that enables enhanced or more efficient performance from the electric transmission system, including, but not limited to, dynamic line rating, advanced power flow control technology, topology optimization and advanced reconductoring.
(b) "Advanced reconductors" means hardware technology that can conduct electricity across transmission lines and demonstrate enhanced performance over traditional conductor products.
(c) "Dynamic line rating" means hardware and/or software technologies used to appropriately update the calculated thermal limits of existing transmission lines based on real-time and forecasted weather conditions.
(d) "Advanced power flow control" means hardware and/or software technologies used to push or pull electric power in a manner that balances overloaded lines and underutilized corridors within the transmission network.
(e) "Topology optimization" means hardware and/or software technologies that identify reconfigurations of the transmission grid and can enable the routing of power flows around congested or overloaded transmission elements.
(f) "Electric corporation" and "combination electric and gas corporation" shall have the same meaning as in section two of this chapter.
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD13870-02-4
(g) "Transmission" shall have the same meaning as "major electric transmission facility" as defined in section one hundred thirty-seven of this chapter.
2. For proceedings before the commission in which an electric corporation or combination electric and gas corporation proposes capital improvements or additions to the transmission system, the department may authorize such electric corporations or combination electric and gas corporations to conduct a cost-effectiveness analysis of multiple strategies, including, but not limited to, the deployment of grid enhancing technologies, and advanced reconductoring. Where grid enhancing technologies or advanced reconductoring, whether in combination with or instead of other capital investments, offer a more cost-effective strategy to achieve transmission goals, including, but not limited to, distributed energy resource interconnection, the commission may approve the deployment of grid enhancing technologies or advanced reconductoring as part of the overall solutions strategy.
3. As part of a proceeding before the commission in which it proposes capital improvements or additions to the transmission system, an electric corporation or combination electric and gas corporation may propose a performance incentive mechanism that provides a financial incentive for the cost-effective deployment of grid enhancing technologies or advanced reconductoring.
4. The department shall promulgate any rules and/or regulations it deems necessary to implement the provisions of this section.
5. Beginning five years after the effective date of this section, and every five years thereafter, each electric corporation or combination electric and gas corporation shall report to the federally designated bulk system operator, and the commission on or before September first on the deployment of any grid enhancing technologies or advanced reconductoring in a format determined by the department.
§ 2. Section 1005 of the public authorities law is amended by adding a new subdivision 31 to read as follows:
31. For any transmission facility the authority constructs or upgrades in connection with this section the authority may conduct a cost-effectiveness analysis of multiple strategies, including, but not limited to, the deployment of grid enhancing technologies and advanced reconductoring. Where grid enhancing technologies or advanced reconductoring, whether in combination with or instead of other capital investments, offer a more cost-effective strategy to achieve transmission goals, including, but not limited to, distributed energy resource interconnection, the authority, as deemed feasible and advisable by the trustees and with any necessary approval from the public service commission, is authorized to deploy grid enhancing technologies or advanced reconductoring, as part of the overall solutions strategy.
§ 3. This act shall take effect on the ninetieth day after it shall have become a law.