What's happening
This bill limits construction contract retainage to no more than 5% and allows final invoicing at substantial completion.
Why it matters
Reduces the amount of money withheld (retainage) from contractors and subcontractors. to no more than 5% of the contract sum, improving cash flow for smaller firms and reducing financial strain during projects.
Allows contractors to submit their final invoice at “substantial completion” instead of after all obligations are fulfilled. potentially speeding up the payment process and making it easier for contractors to access funds sooner, especially when minor punch-list items remain.
Limits how much retainage can be withheld throughout the contracting chain (owner, contractor, subcontractor). , ensuring no party withholds more than 5% and preventing compounding retainage percentages that can severely impact lower-tier subcontractors.
Imposes interest penalties (1% per month) for late release of retainage,. which incentivizes prompt payment and offers some protection to contractors and subcontractors against delayed funds, improving payment practices industry-wide.
Albany, before your first meeting.
Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.
Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.
Headline styles
Limit Construction Retainage Fees
Plain English, a few words. Used as the page title.
Sponsors
Senator · Senate District 46
No co-sponsors yet.
History
- Signed chap.657
- Delivered to governor
- Returned to senate
- Passed assembly
- Ordered to third reading rules cal.755
- Substituted for A4167
- Referred to economic development
- Delivered to assembly
- Passed senateVote 47–15
- Ordered to third reading cal.1472
- Committee discharged and committed to rules
- Referred to consumer protection
Companion bill
The same bill in the other chamber. A bill becomes law when one version passes both houses and the governor signs it, so either number can carry it.
Cap Construction Retainage at 5%
Assembly Floor Calendar · Sponsor Pamela J. Hunter
Full text
1 pageUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗
STATE OF NEW YORK
3539
2023-2024 Regular Sessions
IN SENATE
January 31, 2023
Introduced by Sen. BRESLIN -- read twice and ordered printed, and when printed to be committed to the Committee on Consumer Protection
AN ACT to amend the general business law, in relation to payment and retainage in construction contracts
The People of the State of New York, represented in Senate and Assembly, do enact as follows:
Section 1. The opening paragraph of paragraph (a) of subdivision 2 of section 756-a of the general business law, as amended by chapter 417 of the laws of 2009, is amended to read as follows:
A contractor shall be entitled to invoice the owner for interim payments at the end of the billing cycle. A contractor shall be entitled to submit a final invoice for payment in full [upon the performance of all the contractor's obligation under the contract] upon reaching substantial completion, as such term is defined in the contract or as it is contemplated by the terms of the contract.
§ 2. Section 756-c of the general business law, as added by chapter 127 of the laws of 2002, is amended to read as follows:
§ 756-c. Retention. By mutual agreement of the relevant parties an owner may retain [a reasonable amount] no more than five per centum of the contract sum as retainage. A contractor or subcontractor may also retain [a reasonable amount] no more than five per centum for retainage [so long as the amount does not] and in no case shall retainage exceed the actual percentage retained by the owner. Retainage shall be released by the owner to the contractor no later than thirty days after the final approval of the work under a construction contract. In the event that an owner fails to release retainage as required by this article, or the contractor or subcontractor fails to release a proportionate amount of retainage to the relevant parties after receipt of retainage from the owner, the owner, contractor, or subcontractor, as the case may be, shall be subject to the payment of interest at the rate of one percent per month on the date retention was due and owing.
§ 3. This act shall take effect immediately and shall apply to contracts entered into on or after such effective date.
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD07647-01-3
Reflowed for reading: line numbers and page breaks removed. Cite the official text.
Sponsor's memo
Title of bill
An act to amend the general business law, in relation to payment and retainage in construction contracts
Purpose or general idea of bill
This bill would reduce delays occurring in the release of retainage on private construction jobs that have met "substantial completion" requirements.
Summary of provisions
Section one amends section 756-a of the general business law to require that the release of retainage from the contractor is conditional upon the achievement of the substantial completion terms described in the contract.
Section two amends section 756-c of the general business law to limit the amount of retainage to a maximum of 5% of the contract sum and establish a maximum release period for retainage of thirty days after the final approval.
Section three of the bill provides the effective date.
Justification
Under the current law governing private construction jobs, subcontrac- tors are subject to long waiting times, as long as a year after the completion of a construction project, to receive retainage payments. The lack of clarity in existing law results in avoidable disputes, which in turn prolongs the release of retainage payments. This ambiguity creates economic burdens for contractors and subcontractors, many of which are Minority and Women Owned businesses whose work has been completed in compliance with the contract requirements.
This bill would revise the procedures for contract payment of retainage for owners, contractors, and subcontractors, and establish deadlines for the completion of all remaining items by the contractor and subcontrac- tor.
Within 45 days, the private owner shall submit to the contractor a writ- ten list specifying all items remaining to be completed by the contrac- tor as stipulated in the contract. The contractor is required to provide to each subcontractor with a written list of all remaining items to be performed by the subcontractor no later than 5 business days. Mandating that substantial completion on private construction projects be speci- fied in the contract and reforming the contract payment process of retainage would greatly reduce disputes and delays between owners and contractors.
Prior legislative history
2022: A6985B (Cusick)
2019-2020: S.981 referred to Consumer Protection / A.3558 referred to Economic Development (Cusick).
2017-2018: S.8848 referred to Consumer Protection / A.9637 referred to Economic Development (Cusick).
2016: A.10446 referred to Economic Development (Cusick).
Fiscal implications for state and local governments
None to the State.
Effective date
This act shall take effect immediately and shall apply to contracts entered into on and after such effective date.