Require Warehouse EV Chargers

Official title

“Requires certain distribution centers to be equipped with electric vehicle charging stations”

Sponsor Andrew GounardesSD-26+1 co-sponsorAffects Environment & Energy
Status
In Assembly Committee
Energy
Impact
6/10
Moderate
Passage
0%

Bill progress

Step 5 of 7

In Assembly · Energy

What's happening

This bill requires heavy distribution centers in New York to be equipped with electric vehicle charging stations proportional to their size.

Why it matters

  1. Targets large e-commerce warehouses and parcel hubs. The bill specifically applies to "heavy distribution centers" with at least 50,000 square feet used primarily for e-commerce sorting and distribution, meaning major players like Amazon, UPS, and FedEx would likely be affected, but not food wholesalers or manufacturers.

  2. Promotes electrification of last-mile delivery. By requiring charging infrastructure at key distribution points, the bill directly supports the transition of delivery fleets from gas or diesel to electric vehicles, potentially reducing emissions and air pollution in communities near these facilities.

  3. Proportional infrastructure based on facility size. The number of required charging stations will be determined according to the size and operational needs of each warehouse, allowing for scalability and ensuring that larger centers with more delivery vehicles provide more charging capacity.

  4. Enforceable through penalties. Warehouse operators who fail to comply will be subject to penalties under existing state energy law, giving the requirement real enforcement power and incentivizing timely compliance.

The daily · weekday mornings

Albany, before your first meeting.

Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.

Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.

Who cares

  • E-commerce warehouse operators

    Covered distribution centers with at least 50,000 square feet used for warehouse activities would need EV charging stations, and operators could face penalties for violations.

  • Secretary of state and NYSERDA

    The secretary, consulting with NYSERDA’s president, would set charging-station requirements proportional to each covered warehouse’s size and needs.

  • Manufacturers and wholesale food distributors

    Facilities that manufacture or assemble goods on site before distribution, and facilities primarily storing food for wholesale distribution, would be excluded from the bill’s definition of a heavy distribution center.

Headline styles

Require Warehouse EV Chargers

Plain English, a few words. Used as the page title.

Sponsors

Primary sponsor
Andrew Gounardes

Senator · Senate District 26

Chair, Budget And Revenue

1 Co-sponsor

History

  1. Referred to energy
  2. Delivered to assembly
  3. Passed senateVote 39–18
  4. Advanced to third reading
  5. 2nd report cal.
  6. 1st report cal.1178
  7. Referred to energy and telecommunications
  8. Committed to rules
  9. Advanced to third reading
  10. 2nd report cal.
  11. 1st report cal.880
  12. Referred to energy and telecommunications

Full text

2 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗

STATE OF NEW YORK

6301

2023-2024 Regular Sessions

IN SENATE

April 12, 2023

Introduced by Sen. GOUNARDES -- read twice and ordered printed, and when printed to be committed to the Committee on Energy and Telecommunications

AN ACT to amend the energy law, in relation to code requirements for heavy distribution centers

The People of the State of New York, represented in Senate and Assembly, do enact as follows:

Section 1. The energy law is amended by adding a new section 11-111 to read as follows:

§ 11-111. Special code requirements for heavy distribution centers. 1. Definitions. As used in this section, the following terms shall have the following meanings:

(a) "Electric vehicle charging station" shall mean a station that delivers electricity from a source outside an electric vehicle into one or more electric vehicles. An electric vehicle charging station may include several charge points simultaneously connecting several electric vehicles to the station and any related equipment needed to facilitate charging plug-in electric vehicles.

(b) "Heavy distribution center" shall mean a facility that (i) contains at least fifty thousand square feet of total floor space that is used for warehouse activities; and (ii) has as its primary purpose the temporary storage, sorting, and redistribution of goods to fulfill e-commerce orders by receiving shipments of goods from one mode of transport and redistributing those goods via a delivery vehicle. A "heavy distribution center" shall not include any facility where goods are manufactured or assembled on site and temporarily stored prior to distribution, or any facility that has as its primary purpose the temporary storage of food products for wholesale distribution.

(c) "Last mile delivery" shall refer to the final portion of a parcel's journey from a heavy distribution center to a consumer or enduser.

EXPLANATION--Matter in italics (underscored) is new; matter in brackets

[ ] is old law to be omitted.

LBD09534-03-3

(d) "Parcel hub" shall mean a sorting facility at which parcels are received, sorted, and distributed for last mile delivery.

(e) "Person" means an individual, partnership, limited liability company, society, association, joint stock company, corporation, estate, receiver, trustee, assignee, referee or any other person acting in a fiduciary or representative capacity, whether appointed by a court or otherwise, any combination of individuals and any other form of unincorporated enterprise owned or conducted by two or more persons.

(f) "Warehouse operator" shall mean any person that conducts day-today operations at a heavy distribution center, including operations conducted through the use of third-party contractors.

2. Electric vehicle charging stations in heavy distribution centers. (a) All heavy distribution centers subject to the state energy conservation construction code as described in paragraph (b) of subdivision one of section 11-103 of this article shall be equipped with electric vehicle charging stations on and after the effective date of this section.

(b) The secretary of state, in consultation with the president of the New York state energy research and development authority, shall prescribe the required number or numbers of electric vehicle charging stations per heavy distribution center in the code in a manner proportional to the size and needs of such warehouses.

3. Any warehouse operator found in violation of the provisions of this section shall be liable for the penalties prescribed in section 11-108 of this article.

§ 2. This act shall take effect on the one hundred eightieth day after it shall have become a law. Effective immediately, the addition, amendment and/or repeal of any rule or regulation necessary for the implementation of this act on its effective date are authorized to be made and completed on or before such effective date.

Reflowed for reading: line numbers and page breaks removed. Cite the official text.

Sponsor's memo

Title of bill

An act to amend the energy law, in relation to code requirements for heavy distribution centers

Purpose or general idea of bill

To mandate that all heavy distribution warehouses be equipped with elec- tric vehicle charging stations within one year of passage of this act.

Summary of provisions

Section one adds a new section 11-111 to Article 11 of the Energy Law, which sets the State Energy Conservation Construction Code Act, to mandate that all heavy distribution centers subject to the code must be equipped with electric vehicle charging stations. The Secretary of State in consultation with the NYS Energy Research and Development Authority (NYSERDA) shall be responsible for promulgating regulations to effectu- ate the code, including how many stations should be installed at differ- ent types of centers.

Read the full memo (723 words)

Warehouse operators in violation of the act shall be subject to the penalties of Energy Law § 11-108, which provide that persons served with an order to remedy a violation of the code who fail to comply within a certain time frame, and any owner, builder, architect, engineer, contractor, or subcontractor assisting in construction who knowingly violates a provision of the code, can be liable for a fine of up to $1,000 or a maximum of 30 days in jail, or both.

Section two sets the effective date.

Justification

New York set a statutory goal of a zero-emission electricity sector by 2040, including 70 percent renewable energy generation by 2030, in the historic Climate Leadership and Community Protection Act (CLCPA) of 2019. The state legislature later codified in Ch. 423 of 2021 the goal that 100% of medium- and heavy-duty vehicles sold or leased in New York be zero emission vehicles (ZEVs) by 2045. The CLCPA's Final Scoping Plan, the document which details the strategy by which the state is to achieve the CLCPA's carbon emission goals, calls for an even tighter ZEV timeline of 50% of all medium-duty vehicle sales by 2030 and 80% of all heavy-duty vehicle sales by 2035 (Scoping Plan: Full Report, December 2022, New York State Climate Action Council, p.155.).

Heavy distribution warehouses, defined in this act as storage and distribution facilities that are fifty thousand square feet or greater and have as a primary purpose the temporary storage, sorting, and redis- tribution of goods to fulfill e-commerce orders via delivery vehicles, are responsible for a disproportionate amount of medium- and heavy-duty vehicle traffic in disadvantaged communities. These facilities, which are frequently hundreds of thousands of square feet wide, have a much larger environmental footprint in the overnight delivery age than their predecessor sites. Clustered largely in manufacturing "as-of-right" zones, these facilities attract bigger, and thus more polluting, trucks, and at greater volumes, than a traditional parcel hub. It is only appro- priate therefore, that they be subject to some basic code requirements so that the heavily polluting fleets that they attract have a chance of transitioning to 100% ZEV models by 2045.

This bill would create the policy, recommended on page 417 of the Final Scoping Plan, that all heavy distribution facilities subject to the State Energy Conservation Construction Code have some kind of ZEV charg- ing infrastructure in place. As prescribed in paragraph (b) of subdivi- sion one of section 11-103 of Article 11 of the Energy Law (also known as the the State Energy Conservation Construction Code Act) , the code applies only to construction of new buildings or additions or alter- ations to existing buildings, meaning that existing warehouses with no plans to retrofit would not need to undergo construction just to comply with the bill. Warehouse operators, or their architects and contractors, who knowingly violate the act and refuse to remedy a violation would be subject to the penalties of § 11-108 of the Energy Law/Code Act.

This bill represents a simple step forward on our state's path to a zero-emission electricity sector. In providing that all new or retrofit- ted warehouses have ZEV charging infrastructure for their trucking fleets, we can help ease the trucking industry's transition away from fossil fuels while ensuring that New York is able to meet the carbon neutrality goals of the landmark CLCPA.

Prior legislative history

None

Fiscal implications

TBD

Effective date

This act shall take effect on the one hundred eightieth day after it shall have become a law.