Skip to content
S6881Senate2023-2024 SessionSame asA7611

Allow Utility Line Connections

Official title

“Explicitly permits the standard utility interconnection of sub-transmission lines for particular projects”

Sponsor James SkoufisSD-42Affects Environment & Energy
Status
In Senate Committee
Energy And Telecommunications
Impact
7/10
Significant
Passage
0%

Bill progress

Step 2 of 7

In committee · Energy And Telecommunications

What's happening

This bill allows distributed energy generation projects to connect to utility sub-transmission lines if all state and federal requirements are met.

Why it matters

  1. Expands grid access for renewables. By explicitly allowing distributed generation projects (like solar and small wind) to connect at the sub-transmission level, the bill removes a previous barrier, making it easier for clean energy projects to deliver power where it’s needed.

  2. Potential to speed up clean energy deployment. Allowing these connections under the same process as larger transmission-level projects could reduce bureaucratic delays, helping more projects come online faster and supporting New York’s climate goals.

  3. May lead to lower costs and more local energy. With broader grid access, distributed generators can serve local demand more efficiently, potentially lowering distribution costs for utilities and consumers and improving grid resilience.

  4. Clarifies legal uncertainties. The legislation overrides any conflicting rules or guidelines, providing regulatory clarity for developers and utilities, which could encourage more investment in distributed energy resources.

The daily · weekday mornings

Albany, before your first meeting.

Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.

Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.

Who cares

  • Distributed generation developers

    The bill would allow projects covered by the state's Standardized Interconnection Requirements to connect to utility distribution systems at the sub-transmission level if they meet all other state and federal requirements.

  • Electric utilities

    Utilities would have to allow qualifying sub-transmission connections and use the same interconnection process as at the transmission level.

  • State energy regulators

    The bill would override conflicting laws, rules, regulations, policies or guidelines that prevent these qualifying sub-transmission connections.

Headline styles

Allow Utility Line Connections

Plain English, a few words. Used as the page title.

Sponsors

Primary sponsor
James Skoufis

Senator · Senate District 42

Chair, Investigations And Government Operations

No co-sponsors yet.

History

  1. Referred to energy and telecommunications
  2. Referred to energy and telecommunications

Companion bill

The same bill in the other chamber. A bill becomes law when one version passes both houses and the governor signs it, so either number can carry it.

A7611Assembly

Allow Easier Power Line Connections

In Assembly Committee · Energy · Sponsor Steve Stern

Impact 7 · Significant0% to pass

Full text

1 pageUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗

STATE OF NEW YORK

6881

2023-2024 Regular Sessions

IN SENATE

May 12, 2023

Introduced by Sen. SKOUFIS -- read twice and ordered printed, and when printed to be committed to the Committee on Energy and Telecommunications

AN ACT to amend the energy law, in relation to explicitly permitting the standard utility interconnection of sub-transmission lines for particular projects

The People of the State of New York, represented in Senate and Assembly, do enact as follows:

Section 1. The energy law is amended by adding a new section 21-107 to read as follows:

§ 21-107. Interconnection at sub-transmission lines. Notwithstanding any law, rule, regulation, policy or guideline to the contrary, all forms of energy considered distributed generation under the state's Standardized Interconnection Requirements (SIR) shall be allowed to connect to the utilities distribution system at the sub-transmission level provided that the generator has met all other state and federal requirements. The process for such interconnection shall proceed in the same method and fashion as interconnections at the transmission level.

§ 2. This act shall take effect immediately.

EXPLANATION--Matter in italics (underscored) is new; matter in brackets

[ ] is old law to be omitted.

LBD11336-01-3

Reflowed for reading: line numbers and page breaks removed. Cite the official text.

Sponsor's memo

Title of bill

An act to amend the energy law, in relation to explicitly permitting the standard utility interconnection of sub-transmission lines for partic- ular projects

Purpose

This bill seeks to provide clarity that certain distributed energy sources may interconnect to a sub transmission line in the same way they currently interconnect to other such lines.

Summary of provisions

Section 1. Makes clear that despite other policies to the contrary, distributed generation projects may interconnect to a sub transmission line provided they meet all other applicable rules and standards.

Section 2. Sets forth the effective date.

Justification

New York State is a leader in the fight against climate change and has worked toward crafting state policies that will allow for the transition to 100% renewable power by the year 2050. Article 3 of the State Energy Law among other documents make these goals clear, particularly consider- ing the adoption of the Climate Leadership and Community Protection Act (CLCPA).

It is in the best interest of the State of New York to adopt policies that reasonably advance the goals outlined in the CLCPA and create uniformity in their application across all utility service territories. This legislation seeks to address one small obstacle in the intercon- nection process for distributed renewable generation. Some State utili- ties allow a renewable developer to interconnect at the sub transmission level and others do not. This incongruence causes delays and additional costs in the system that can ill afford them, given our 2050 goals. This legislation is needed to make clear that distributed generation must be allowed to interconnect at the sub transmission levels in all areas of the State of New York. This will encourage faster development and deployment and assist the state in further reducing emissions and its dependence on fossil fuels.

Legislative history

New Bill

Fiscal implications

None

Effective date

This act shall take effect immediately