What's happening
This bill allows adjustments to state construction and commodity contracts to provide financial relief for contractors facing unexpected construction materials price increases.
Why it matters
Helps stabilize public construction projects. by allowing contract adjustments when material costs rise unexpectedly, which can prevent contractors from abandoning projects or going bankrupt, thus avoiding costly delays or project failures for taxpayers.
Applies retroactively to contracts awarded before April 1, 2020,. but only covers materials purchased after March 1, 2020—this targets relief specifically at contracts and purchases impacted by the COVID-19 pandemic supply disruptions.
Includes both upward and downward adjustments,. meaning if material prices later decrease, contractors must also reduce their contract prices, protecting the state from overpaying and ensuring fairness.
Requires transparency and oversight,. as adjustments must be supported by documented evidence (such as national economic indexes) and are subject to approval by state officials and public inspection, reducing the risk of abuse or fraud.
Albany, before your first meeting.
Every bill that moved yesterday, summarized in a sentence and ranked by impact. The Albany Scorecard follows on Sundays.
Free. Unsubscribe in one click. Want alerts on specific bills? Create an account.
Headline styles
Help Contractors With Material Costs
Plain English, a few words. Used as the page title.
Sponsors
3 Co-sponsors
History
- Substituted by A10109
- Ordered to third reading cal.1818
- Committee discharged and committed to rules
- Reported and committed to finance
- Referred to procurement and contracts
Companion bill
The same bill in the other chamber. A bill becomes law when one version passes both houses and the governor signs it, so either number can carry it.
Help Contractors With Rising Costs
Vetoed · Sponsor Kenneth Zebrowski
Full text
3 pagesUnderlined is new[Struck] is removedOfficial text on nysenate.gov ↗
STATE OF NEW YORK
8844
IN SENATE
April 22, 2022
Introduced by Sen. REICHLIN-MELNICK -- read twice and ordered printed, and when printed to be committed to the Committee on Procurement and Contracts
AN ACT in relation to amending state construction and commodity contracts to provide equitable relief to contractors who have sustained unanticipated expenses by reason of construction materials price escalation; and providing for the repeal of such provisions upon the expiration thereof
The People of the State of New York, represented in Senate and Assembly, do enact as follows:
Section 1. Declaration of policy and statement of purpose. It being in the vital interest of the general public that public works in the state of New York be administered efficiently and at a reasonable and equitable cost; and, the unforeseen emergency of unanticipated escalation in construction materials prices having imposed substantial inequity upon contractors who have heretofore been awarded contracts after public bidding; and, such inequity having threatened the ability of contractors to fulfill contracts so awarded; and, in order to perpetuate the benefits derived by the general public from the existing system of public bidding, and to assure the continuance of the orderly performance of contracts heretofore awarded as a result of such public bidding; and, it being in the best interest to provide equitable relief to those contractors who, having been awarded public contracts, have sustained damage by reason of such construction materials price escalation, this act is hereby enacted.
§ 2. Whenever the terms and conditions of a construction contract awarded by the state of New York or a public benefit corporation based upon bids submitted prior to April 1, 2020 but only for which materials were purchased or invoiced after March 1, 2020, require a contractor to furnish materials in such contract pertaining to such construction materials may be adjusted upon a determination made by the officer of the department, board, agency or public benefit corporation that awarded such contract that there has been an increase in the cost of acquisition by the contractor, subcontractor or supplier of materials of such mate-
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD15088-03-2
rials in excess of five percent, determined as of the time of the award. Such a determination shall be based upon the available evidence, including but not limited to, an appropriate nationally recognized economic index published by the United States department of labor or other appropriate organization. In the case of any state department or agency any such increase in contract price shall be subject to the approval of the state comptroller. Any contractor, subcontractor or supplier of materials who receives an increase in the cost of construction materials shall also be subject to a downward adjustment in construction materials prices for subsequent de-escalation which may result in a price being lower than the original bid price. Any contractor requesting an adjustment shall make application in writing submitting documentary evidence to the office of the department, board, agency or public benefit corporation that awarded the contract establishing such increase in accordance with the requirements of the department, board, agency or public benefit corporation, which evidence shall be subject to public inspection during regular business hours. Any subsequent decrease or de-escalation shall be made upon a determination by the officer of the department, board, agency or public benefit corporation that awarded such contract that there has been a subsequent decrease in the cost of acquisition of such construction materials by the contractor, subcontractor or supplier of materials. Such a determination shall be based upon the available evidence, including but not limited to, an appropriate nationally recognized economic index published by the United States department of labor or other appropriate organization. Upon the agreement of the parties, the contract may be amended in writing to reflect the increased or decreased cost of acquisition of such materials insofar as it exceeds five percent thereof and such contract amendment shall state the amount of adjustment and the basis therefor, but in no event shall direct labor costs, additional profit or overhead be part of such adjustment. To the extent a construction contract is subject to approval by the state comptroller, and as to the form and manner of execution, by the attorney general, every such contract amendment shall be subject to the approval of the state comptroller, and as to form and manner of execution, by the attorney general. No adjustment shall be granted in an amount which, together with any other sum obligated under the contract, shall exceed the money appropriated or otherwise lawfully available for the project.
§ 3. (a) The commissioner of general services in contracting for commodities is authorized, with the approval of the state comptroller, to terminate or suspend for a part of its term any state contract award for the purchase of commodities upon written application for such termination or suspension by the vendor, where extraordinary and unforeseen general market conditions have caused increases in the vendor's costs for construction materials or other physical elements consisting of construction materials to be sold under the contract, where the contract covers materials which were purchased or invoiced after March 1, 2020, and the commissioner of general services determines upon evidence furnished by the vendor as required and deemed to be sufficient by the commissioner that as the direct and sole result of such increases during the term of the contract, which exceed five percent of the contractor's aggregate acquisition costs determined as of the time of the award, the contractor has incurred or will incur an actual net loss on such contract from the estimated sales made under the contract and the contractor would continue to incur such net losses unless the contract is suspended or terminated. Such a determination shall be based upon the available evidence, including but not limited to, an appropriate nationally recognized economic index published by the United States department of labor or other appropriate organization.
(b) The commissioner of general services is further authorized, following the determination made pursuant to the provisions of subdivision (a) of this section that the contractor has incurred or will incur an actual net loss on such contract from the sales made under the contract, to grant an increase or increases in the prices of the commodities specified by the contract, in amounts necessary to prevent further net losses to the contractor on such contract from deliveries to be made thereafter under the contract, as compensation for and not exceeding increases of the contractor's acquisition costs during the contract term. Any such increase in contract prices shall be subject to the approval of the state comptroller. Any contractor who receives an increase in the price of the commodities shall also be subject to a downward adjustment in the price of the commodities for subsequent de-escalation which may result in a price being lower than the original bid price. Any subsequent decrease or de-escalation shall be made upon a determination by the officer of the department, board, agency or public benefit corporation that awarded such contract that there has been a subsequent decrease in the cost of acquisition of such construction materials by the contractor, subcontractor or supplier of materials. Such a determination shall be based upon the available evidence, including but not limited to, an appropriate nationally recognized economic index published by the United States department of labor or other appropriate organization.
(c) All records, books and documents of the contractor which are related or useful to the determinations made by the commissioner of general services and to the approval of the state comptroller hereunder shall be subject to audit and examination by the state comptroller.
§ 4. This act shall take effect immediately and shall expire and be deemed repealed June 30, 2023.
Reflowed for reading: line numbers and page breaks removed. Cite the official text.
Sponsor's memo
Title of bill
An act in relation to amending state construction and commodity contracts to provide equitable relief to contractors who have sustained unanticipated expenses by reason of construction materials price esca- lation; and providing for the repeal of such provisions upon the expira- tion thereof
Purpose
The bill will allow contractors who submitted bids to the State of New York or a public benefit corporation prior to April 1, 2020 to receive an adjusted contract on materials costs where the price escalated in excess of five (5) percent upon invoice or purchase of said materials from the original bid.
Summary of provisions
Section 1 is the declaration of policy and statement of purpose.
Section 2 will enable contractors holding construction contracts as awarded by the State of New York or a public benefit corporation upon bids submitted prior to April 1, 2020 but only for which materials were purchased or invoiced after March 1, 2020, that experienced an increase in the cost of acquisition of such materials in excess of five percent (5%) be able to apply for an adjustment to their contract in order to recoup the increased material costs.
In cases of a state department or agency, any such increase in contract price will require the approval of the state comptroller. Contractors requesting an adjustment will have to apply in writing, submitting evidence to the department, board, agency or public benefit corporation that awarded the contract. This section also accounts for changes to be made if there is a de-escalation in costs from the original bid.
Section 3 authorizes the Commissioner of the Office of General Services (OGS), with approval from the state comptroller, in contracting for commodities to terminate or suspend for a part of its term any state contract award for the purchase of commodities upon written application where increases in cost due to unforeseen circumstances have cost increases in excess of five percent (5%) in the vendor's costs for construction materials or other physical elements that were purchased or invoiced after March 1, 2020, that will result in a net loss for the contractor unless the contract is suspended or terminated.
In cases where the contractor has incurred or will incur net losses, the Commissioner of OGS is authorized to grant an increase or increases in the prices of the commodities specified in the contract to prevent further loss to the contractor. This also applies to the ability to make adjustments should prices de-escalate.
Requires contractor documentation including records, books and documents related to any adjustments to be made by the commissioner of OGS that are subject to the approval of the state comptroller to be required to be available for audit and examination.
Section 4 provides for the effective date.
Justification
Similar language was enacted by the State Legislature in 2004 to aid contractors with sharp increases in steel prices. This language is once again put forth to ensure that entities who entered into construction contracts after public bidding with New York State or its public benefit corporations prior to April 1, 2020, in which said contracts do not include clauses to allow for significant price shifts in material costs are not saddled with losses due to the unforeseen impact of the COVID-19 global pandemic on the world's supply chain on the acquisition of mate- rials.
Legislative history
New bill.
Fiscal implications
To be determined.
Effective date
The act shall take effect immediately and shall expire and be deemed repealed on June 30, 2023.